Estimation, Valuation & Construction Management MCQs for APSC PWD and WRD JE 2025

Estimation, Valuation & Construction Management MCQs for APSC PWD and WRD JE 2025

Estimation, Valuation & Construction Management MCQs for APSC JE 2025

30 Estimation, Valuation & Construction Management MCQs for APSC JE PWD & Water Resources 2025

Topics Covered

  • Estimation and Costing
  • Valuation
  • Construction Planning and Scheduling
  • Construction Techniques and Equipment
  • Project Management
Topic: Estimation and Costing
1. What is the primary purpose of a detailed estimate?
Answer: b) To calculate exact quantities and costs
A detailed estimate provides precise quantities of materials and labor for accurate cost calculation.
Topic: Estimation and Costing
2. Which unit is used for estimating plastering work?
Answer: b) Square meter
Plastering is measured by surface area, typically in square meters.
Topic: Estimation and Costing
3. What is the standard deduction for openings in brickwork estimation?
Answer: a) No deduction for openings below 0.1 sq.m
Small openings (less than 0.1 sq.m) are typically ignored in brickwork calculations.
Topic: Valuation
4. What is the book value of a property?
Answer: b) Original cost minus depreciation
Book value reflects the asset’s cost adjusted for depreciation over time.
Topic: Valuation
5. Which method is used for valuing rental properties?
Answer: c) Rental method
It estimates value based on the annual rental income of the property.
Topic: Valuation
6. What is the scrap value of a building?
Answer: b) Value of materials after demolition
Scrap value is the residual value of materials post-demolition, typically 10% of construction cost.
Topic: Estimation and Costing
7. What does the term 'contingency' cover in an estimate?
Answer: b) Unforeseen expenses
Contingency (3-5% of total cost) accounts for unexpected costs during construction.
Topic: Estimation and Costing
8. Which method is used for estimating road construction?
Answer: a) Centerline method
It calculates quantities based on the road’s centerline length for accuracy.
Topic: Valuation
9. What is the purpose of depreciation in valuation?
Answer: b) Account for wear and tear
Depreciation reduces the property’s value based on age and condition.
Topic: Estimation and Costing
10. What is a rate analysis used for?
Answer: b) Calculating cost per unit of work
Rate analysis breaks down material, labor, and overhead costs for each work item.
Topic: Valuation
11. Which factor does NOT affect the valuation of a property?
Answer: c) Owner’s nationality
Valuation depends on objective factors like location, age, and demand, not personal attributes.
Topic: Estimation and Costing
12. What is the plinth area of a building?
Answer: b) Built-up area at ground level
Plinth area includes the entire floor area within external walls at the ground level.
Topic: Valuation
13. What is the sinking fund method used for?
Answer: b) Calculating future replacement cost
It accumulates funds over time to replace an asset at the end of its life.
Topic: Estimation and Costing
14. Which item is included in a preliminary estimate?
Answer: b) Approximate cost of the project
Preliminary estimates provide a rough cost for initial planning.
Topic: Valuation
15. What is the market value of a property?
Answer: b) Price it fetches in an open market
Market value reflects what buyers are willing to pay under current conditions.
Topic: Construction Planning and Scheduling
16. What is the critical path in a project?
Answer: b) Longest path determining project duration
The critical path has no float and dictates the project’s minimum completion time.
Topic: Construction Planning and Scheduling
17. What does PERT stand for?
Answer: a) Project Evaluation and Review Technique
PERT is used for scheduling and managing projects with uncertain task durations.
Topic: Construction Techniques and Equipment
18. Which equipment is used for compacting soil?
Answer: b) Roller
Rollers compact soil to increase its density and stability.
Topic: Project Management
19. What is the primary purpose of a Work Breakdown Structure (WBS)?
Answer: b) Divide project into manageable tasks
WBS breaks down complex projects into smaller, trackable components.
Topic: Construction Planning and Scheduling
20. What is float in a project schedule?
Answer: a) Extra time for non-critical tasks
Float allows flexibility in scheduling tasks not on the critical path.
Topic: Construction Techniques and Equipment
21. Which construction technique is used for deep foundations?
Answer: b) Pile foundation
Piles transfer loads to deeper, stable soil layers.
Topic: Project Management
22. What is the main objective of quality control in construction?
Answer: b) Ensure work meets specifications
Quality control verifies that materials and workmanship adhere to standards.
Topic: Construction Planning and Scheduling
23. What is a Gantt chart used for?
Answer: b) Project scheduling
Gantt charts visualize task timelines and dependencies.
Topic: Construction Techniques and Equipment
24. Which material is primarily used in precast concrete construction?
Answer: b) Reinforced concrete
Precast concrete uses reinforced concrete for strength and durability.
Topic: Project Management
25. What does a project manager monitor during execution?
Answer: b) Time, cost, and quality
These are the key parameters for successful project delivery.
Topic: Construction Planning and Scheduling
26. What is crashing in project management?
Answer: b) Reducing project duration by adding resources
Crashing accelerates tasks but may increase costs.
Topic: Construction Techniques and Equipment
27. Which equipment is best suited for lifting heavy loads to great heights?
Answer: b) Tower crane
Tower cranes are designed for heavy lifting in high-rise construction.
Topic: Project Management
28. What is a risk register used for?
Answer: b) Identifying and managing risks
It lists potential risks and mitigation strategies.
Topic: Construction Planning and Scheduling
29. What is the purpose of a bar chart in construction?
Answer: b) Visualizing task durations
Bar charts (like Gantt charts) show task start, end, and duration.
Topic: Construction Techniques and Equipment
30. Which technique improves concrete strength in cold weather?
Answer: b) Steam curing
Steam curing accelerates hydration, enhancing strength in low temperatures.